Formin Hydropower Plant Upgrade Boosts Capacity

Posted

Dravske elektrarne Maribor (DEM), Slovenia’s largest renewable energy producer, has awarded ANDRITZ a contract for the complete refurbishment of the Formin hydropower plant, a run-of-river facility commissioned over 45 years ago. The modernization will replace two turbines and generators and upgrade related electromechanical equipment, increasing the plant’s total capacity from 116 MW to 130 MW.

Enhancing Slovenia’s Renewable Energy Backbone

DEM operates a hydropower fleet of nearly 600 MW that generates about 2,800 GWh annually, providing close to 25% of Slovenia’s electricity production. As part of the HSE Group, DEM plays a central role in Slovenia’s energy security and renewable energy strategy.

Slovenia has committed to raising the share of renewables in final energy consumption to at least 27% by 2030, in line with EU targets (European Commission). Hydropower remains a cornerstone of this strategy, offering dispatchable generation to balance growing solar and wind capacity.

A Broader European Trend

Across Europe, hydropower plants are reaching the end of their original design life. The International Hydropower Association estimates that nearly 60% of Europe’s hydropower capacity is over 40 years old, creating demand for modernization to extend lifespans, improve efficiency, and integrate with today’s digital grid requirements.

Upgrades often go beyond mechanical replacements, incorporating digital control systems, environmental safeguards, and performance optimization tools. This modernization trend allows utilities to expand output without the land use and ecological challenges of new dam construction.

Scope of Work

ANDRITZ’s contract includes:

  • Design and manufacturing of two new turbines and generators
  • Installation, testing, and commissioning of uprated units
  • Auxiliary systems to support reliable long-term operation

The work will be carried out at ANDRITZ’s Austrian facilities, supported by its global engineering network.

Why It Matters

  • Capacity Gains: Increasing Formin’s output to 130 MW boosts DEM’s contribution to national renewable targets.
  • Reliability: Refurbishments extend the lifespan of critical assets, reducing the need for costlier greenfield projects.
  • Sustainability: Modernizing existing plants provides additional clean electricity without expanding environmental footprints.
  • Grid Stability: Hydropower upgrades enhance system flexibility, balancing variable solar and wind resources.
Environment + Energy Leader